To:  Victory Heights Property Owners

 

From:  Jxxx

           

Cc:  Dusty Parsons

         David Tenney

 

Date:  June 27, 2006

 

Subject:  Victory Heights County Road Maintenance District Petition Update

 

We have good news!  We have received sufficient petition signatures to initiate the Maintenance District (MD) formation process with Navajo County.  On June 20, we submitted the signed petitions to the Navajo County Department of Public Works. 

Specific Results

We received petition signatures from 43 property owners, representing 59% of all owners within the proposed MD, and also representing 57% of the acreage within the MD.  Also, based on email and telephone inputs, we expect to receive two or three additional petition signatures. 

 

Note to procrastinating property owners:  Please send in your signed petitions!   Even though we currently have enough to proceed with the formation of the MD, these signatures could become important if problems arise during the petition verification process (see Next Steps below).

 

It was especially gratifying to us to observe that about a half dozen of the owners who had responded negatively to our initial survey, changed their minds and signed petitions.  We feel that this indicates growing support for the MD, as people are taking the time to carefully consider the options.

Next Steps

Over the next few weeks, we expect that Navajo County will perform the following actions:

  1. They will verify that the submitted petition meets their requirements.
  2. If there are no problems, they will formally present the petition to the Board of Supervisors at their meeting on July 17 and request that a hearing date be set.
  3. If the Board of Supervisors agrees to proceed, they will schedule a public hearing on this matter to occur within 40 days of their July 17 meeting.  Notice of this hearing will be published in the newspaper and mailed to all owners.  Any objections or protests will be heard at the hearing.
  4. If the results of the hearing are positive, the MD will be formed by formal order of the Board of Supervisors at the close of the hearing.  (Our goal is to form the MD early enough this fall to allow funds to be collected as part of our 2007 taxes.)

More Good News

You may recall from our previous letters that we expected that the MD would not be able to begin operations until late 2007 after tax funds become available, even if it is approved this year. 

 

Navajo County has informed us that they have identified $5,000 which can be made available to us shortly after the MD is approved (pending formal approval of the County budget).  These funds would allow the MD to begin limited operation later this year (likely to be road grading only, with little or no improvements), a year earlier than we had expected!  Note also that these funds are a grant, not a loan, and would not need to be “paid back” after tax funds become available to the MD. 

 

We would like to express our thanks to David Tenney, Navajo County Supervisor representing our District, and to Dusty Parsons, Navajo County Director of Public Works, for identifying these funds.

In Conclusion

We expect that this will be our final letter to you for quite some time, as the next steps in this process are the responsibility of Navajo County.  They will be communicating with all of us as required to complete this process.

 

If you have any questions, please contact Sam xxx or Jim xxx  You can also send email to Jim at xxx

 

Thank you for your petition responses and your support throughout this process. 

 

Sincerely,

 

 

xxx                                           xxx